City of Walla Walla
Home GO Menu2020 US 12 – 2nd Avenue to Airport Way Corridor Study
April 6, 2020
Project Update
The final consultant recommendation and agency adoption are anticipated in early 2020. With the feedback gathered from the latest September public open house and Council meetings, the consultant and technical advisory committee (TAC) were able to narrow the study alternatives to two options, each of which address the project’s stated purpose and needs:
1) Diamond interchange at US12/Clinton with minor upgrades at US 12 / Wilbur Avenue 2) Dual lane roundabouts at US12/Clinton Street and US12 / Wilbur Avenue
An additional TAC meeting is anticipated to develop a recommended alternative that will be considered for adoption by the various partner agencies sometime in early 2020.
October 2018................................................ (COMPLETED) Consultant Contract awarded by City
Council January – March 2019 ............................................. (COMPLETED) Evaluate Existing & Future Conditions
March - August ................................................................. (COMPLETED) Alternatives Evaluation Process
September - December................................................................................................ Preferred Alternative
January – February 2020............................................................ Final Report and Adoption by City Council
What is this project going to accomplish?
This transportation study has analyzed existing traffic conditions on US 12 between 2 nd Avenue and Airport Way in order to develop recommendations for intersection and system improvement(s) that would best accommodate the anticipated future traffic patterns and growth, while addressing safety for all other users of the roadway
How will this project be funded?
Consultant contract cost is $246,711.41, which is being split as follows:
WSDOT - $100,000
City of Walla Walla - $48,903.80
Walla Walla County - $48,903.80
Port of Walla Walla - $48,903.80