Updated:  March 10, 2025

Project Update

WSDOT completed planned improvements along 9th Avenue (SR-125) between the railroad tracks and Orchard Street in 2023. The final phase, which will extend the sidewalk across the railroad tracks on both sides of 9th Avenue/SR-125, is scheduled for completion in 2025 and 2026.

What is this project going to accomplish?

This Washington State Department of Transportation (WSDOT) project now consists of three stages:

  • The first (completed) stage constructed a roundabout at the SR-125 (9th Avenue)/Plaza Way/The Dalles Military Road intersection to improve traffic flow and reduce the risk of collisions.  This first stage also included improving Plaza Way south to Village Way and the replacement of the traffic signal at Plaza Way and Tietan Street. 
  • The second (current) stage was bid as part of a larger overall paving project on SR-125.  It will extend sidewalk north from the railroad tracks to the existing sidewalk near Grocery Outlet on the west side of 9th Avenue.  Curb, gutter, and storm drainage is also included.  Additionally, an enhanced pedestrian crosswalk will be installed at Orchard Street.
  • The third and final stage of the project will upgrade the railroad crossing on SR-125 (9th Avenue) and connect sidewalks on both sides of SR-125 (9th Avenue) to the north. 

Project Schedule

According to WSDOT and Columbia Railroad, several railroad upgrades will occur throughout 2025 that will not impact public travel. Short-duration road closures of SR-125 (9th Avenue) and Tietan Street are anticipated in mid/late September 2026, when the railroad crossings are replaced.

How is this project being funded?

Predominately funded by $3.9M in State funds and $3.2M in Federal funds.