Project Update
Construction is complete, and the roadway is open to the public. Please stop by to see the new bridge and visit the businesses on Spokane Street.
Thank you to Harry Johnson Plumbing and Excavation, and the local businesses for working together for a successful project.
What is this project going to accomplish?
This project replaced the existing load restricted bridge, and complete streetscape and utility improvements along Spokane Street between Alder Street and Main Street
How will this project be funded?
The project is estimated at $2.23 million and is funded as follows:
- $1.27 million – Federal Bridge Grant
- $577K – Local Funding (Grant match)
- $250K – Port Economic Development Grant