Updated: Dec. 9, 2025
2026 Pavement Maintenance Projects
The following planned projects are subject to budget, availability of labor, and/or utility repair needs:
Grind/Inlay
- Howard Street – Alder Street to Newell Street
- Par 72 – Rees Avenue to End of Curb
- The Dalles Military Road – 9th Avenue West 1000'
- Fern Avenue – Yellowhawk Creek North 900’
Overlays
- 12th Avenue – Rees Avenue to Elm Street
- Moore Street – 12th Avenue to 13th Avenue
- Paine Street – 12th Avenue to 13th Avenue
- Elm Street – 12th Avenue to 13th Avenue
- Woodlawn Street – Bryant Avenue to Woodbury Lane
- Chestnut Street – Division Street to Fern Avenue
- Par 72 Drive – End of Curb to Club House
Strikethrough = work completed
Definitions
- Rebuild: Excavation of the existing street to the roadbed and the rebuilding of the roadbed and surface layers of the street.
- Overlay: Application of a surface layer of asphalt or asphaltic concrete.
- Grind/Inlay: Grind 2" of existing asphalt and inlay new asphalt.
- Skin Pave: A thin asphalt lift is placed directly on pavement without any milling.
- Spot/Rut Repair: The damaged portion of the roadway is removed, and the underlying issue(s) that cause the failure are remedied before the patch is replaced with new asphalt.
- Crack Sealing: The injection of hot tar or asphalt into cracks and paving seams.
- HMA: Hot mix asphalt